09 Jun 2023 [2023] EWHC 1394 (Admin); [2023] PTSR 1735; [2023] WLR(D) 253, KBD (Chamberlain J)
09 Jun 2023 [2023] EWHC 1394 (Admin); [2023] PTSR 1735; [2023] WLR(D) 253, KBD (Chamberlain J)
PLANNING — Development — Planning permission — Planning permission granted for construction of solar farm and substation — Planning permission refused for second solar farm and associated infrastructure to be connected to first — Developers’ appeals raising issue whether solar farms together amounting to nationally significant infrastructure project (“NSIP”) requiring development consent under separate statutory regime — Appeal inquiry adjourned for application to court to determine whether development comprising NSIP — Whether court having power to make such determination — Whether cables and substation connecting two solar farms part of “generating station” — Whether second solar farm “extension” of first — Whether development comprising NSIP — Electricity Act 1989 (c 29), ss 36(9), 64(1) — Town and Country Planning Act 1990 (c 8), s 78 — Planning Act 2008 (c 29), ss 14(1)(a), 15(1)(2)(c), 55(3)(c), 115(1), 235(1)
[2023] EWHC 1394 (Admin); [2023] PTSR 1735; [2023] WLR(D) 253, KBD
To cancel your subscription, please click the Cancel subscription button below and we will process your request as soon as possible.
We use cookies on this website, you can read our Privacy and Cookies Policy. To use website as intended please Accept Cookies